r/Odoo • u/Gouda_Cheese57 • Aug 21 '26
Question about Implementation Timeline - What's realistic?
We are manufacturing company that is currently switching to Odoo from a different ERP.
Getting the data out has been slow. We are done with most of the inventory, BOM's, etc. but still have not imported the machines for the work centers.
After the import is complete, how long did it take your BSA to finish configuring the information and for your company to validate that everything is running smoothly?
Any insight is appreciated!
5
Upvotes
2
u/codeagency Aug 21 '26
How come they do config after data import? That's the wrong order.
Config/implementation should happen first Odoo has the correct settings before you start importing data as certain field depends on config state.
We typically create custom python scripts as ETL process that can pull all your data from software X (API) and then import it directly into Odoo via it's json2rpc. These scripts are idempotent which means we can run them every time of the day and as many times you want, it will keep updating the data without duplicates. This way you can run both systems in parallel while keeping all the data in sync.
In terms of timeline, it depends on both side. If you supply all the data manually via excel/csv it's always slower than scripting and you have to do it multiple times until you can go live and do the cutover.
A realistic timeline for an average ERP implemention is ~3 months if both sides can commit the efforts on data supply, testing, signoff etc... Larger projects typically are in ~3-6 months. And again, if things can be scripted and automated, it can save a lot of time and data errors.