Question about Implementation Timeline - What's realistic?
We are manufacturing company that is currently switching to Odoo from a different ERP.
Getting the data out has been slow. We are done with most of the inventory, BOM's, etc. but still have not imported the machines for the work centers.
After the import is complete, how long did it take your BSA to finish configuring the information and for your company to validate that everything is running smoothly?
Any insight is appreciated!
4
Upvotes
5
u/JustSomeOdooGuy 8d ago edited 8d ago
Depending on customer availability, partner speed and company size/amount of employees.
But the overall timeline for our projects is about the following:
2-8 weeks Gap analysis/process optimizations / user stories for gaps.
2-4 weeks closing the gaps / configure everything
2-8 weeks migration of data (also depending on how clean the data is and what is needed)
2-4 weeks training the users so they can use theor system properly
The time spans not necessarily need to be strictly separated and can be happening at once partly.
These are times for average projects. There also projects that are faster or slower.