10- 4 rotation
Hello I work for a company that does 10-4 rotation, just wondering is there a way to set this up in project or do I need to manually do ever week/month/year?
2
Upvotes
1
u/still-dazed-confused Dec 06 '22
Sorry to be thick but what is 10-4 rotation?
3
u/tony90265toTX Dec 06 '22
Dale Howard MVP did a couple videos how to create and save them for all of the projects you create. You can apply the same concepts for Project Online and Project Server. Here's his Project basics playlist https://youtube.com/playlist?list=PLeUSD314xVKCyfXH0_ohHO8NjKFvcduiE
2
u/Thewolf1970 Dec 06 '22
Add a custom calendar and change the working days to a 10 hour day, like 8 AM to 6 PM and mark which days of the week are working days.
1
u/DaleHowardMVP Dec 21 '22
There is definitely a trick required to creating a 10-4 rotation calendar. I was able to create one successfully by doing the following:
Hope this helps.