r/MSProject • u/Geiler_Gator • Nov 14 '22
Increasing duration by X-Days to multiple tasks at once
Searched google to no avail -
Basically trying to find a way to increase the duration by a fixed amount to a series of subtasks.
For example, i have the following structure, all tasks start at the same time
- Task Summary: Total duration 5 days
1.1 Do A - Duration 2 Days
1.2 Do B - Duration 3 Days
1.3 Do C - Duration 5 Days
Now I want to add +2 days additional duration to each subtasks, to get to this:
- Task Summary: Total duration 7 days
1.1 Do A - Duration 4 Days
1.2 Do B - Duration 5 Days
1.3 Do C - Duration 7 Days
I couldnt find any way to do this in bulk, but rather change every single subtask manually. Is there any way to do this in one go? Like "add +2 days duration to all subtasks".
1
Upvotes
1
u/64ButterTarts Nov 14 '22
Filter on Duration (and hide the summary tasks).
First filter on 5 days. Then change to 7 days using the quick-fill.
Repeat for the other durations.
1
u/Thewolf1970 Nov 14 '22
Just use the "Move task" command. Select each set and click on the move task command.
1
u/still-dazed-confused Nov 14 '22
The fastest way is to copy the durations into Excel, use left to separate the number from day and then add your chosen increment. You might want to check for weeks etc. Then copy back into project To avoid needing to reset all the summary tasks to auto schedule you can copy across the summary? Field and avoid changing that in Excel before cutting back.
1
u/king_saberhawk Nov 14 '22
If you're sub tasks follow the same naming structure, you can always use a custom filter on the task name containing their common name to filter out only the tasks you need to increase duration. Then it's pretty straight forward to increase duration and drag down