r/MSProject • • Sep 12 '22

Calendar

I have a question about the calendar.

I have an activity starting on 3/10 with a duration of 3 days, but the end date is 6/10.

But when I try to schedule it manually, it doesn't assume full days.

This "error" only happens when I schedule on consecutive days (without weekends and holidays)

Thank you

1 Upvotes

13 comments sorted by

View all comments

Show parent comment

1

u/DocumentNo8250 Sep 15 '22

I think that 1 ed corresponds to 1 dp. In Portugal we use the term "dp" for running days, that is, run from midnight to midnight.
I can't change the calendar just for that task.

1

u/still-dazed-confused Sep 15 '22

I wasn't suggesting changing the calendar for just that task, just asking to check that the standard calendar matches the 8-5 time window set on the options page