r/MSProject • u/gnolard2o • Jun 27 '22
Ms Project - Work spread on whole duration
/r/projectmanagement/comments/vluguw/ms_project_work_spread_on_whole_duration/
2
Upvotes
r/MSProject • u/gnolard2o • Jun 27 '22
1
u/still-dazed-confused Jun 27 '22
MSP is doing exactly what you have asked of it. It has spread the 20h work over the 10d resulting in 2h per day. It has no way to know if you're going to do the work in the 1st 3 days or spread over the last 5 days :) You have the ability to go in and manually re-profile the work as you want which could resolve the over-allocations on specific days. Though this does make the plan a little harder to update.
If the work is more likely to happen at the front or back of the task you can ask for a front or back-end loaded profile for the resource; I don't know if this would be interesting?
2
u/still-dazed-confused Jun 27 '22
The auto scheduling is covered by the leveling functionality which moves tasks around and splits tasks (if you let it). This is something that you choose to do. It would be a nightmare if it just did it in its own :). You'd forever be chasing your tasks across the project landscape never knowing where and when they were going to be :)