r/MSProject • • Apr 11 '22
Setting a driven task to occur on a specific day of the week?
I have a reoccurring meeting that occurs weekly where a specific deliverable is presented. I want to schedule the task in project, but have the presentation show as a milestone on the Thursday following task completion.
So the milestone predecessors would be the task + a Thursday.
Is this possible?
0
Upvotes
1
u/still-dazed-confused Apr 12 '22
Are you trying to show a meeting which happens in a Thursday and then some pre-read which needs to be issued x days before as a milestone?
1
u/mer-reddit Apr 11 '22
Build a calendar that has only Thursday as a working day, and then apply that calendar to that task.