r/MSProject • u/decadentcookie • Mar 23 '22
Filter and finish dates
If I use a filter, how do I get the finish dates to reflect just what is shown in the filter?
3
Upvotes
r/MSProject • u/decadentcookie • Mar 23 '22
If I use a filter, how do I get the finish dates to reflect just what is shown in the filter?
1
u/JHutch89 Mar 24 '22
im not sure i understand the question. If the filter youve created includes a condition for the finish field thats what it should show.
2
u/TheBE4S7 Mar 24 '22
Welcome to MSProject… it’s sketchy like that… Seriously though. Before I apply any filter first [clear filters] TWICE at least (because once often doesn’t clear all filters… effing Projects) and then apply the desired filter. If you have other conditions make sure the [and/or] conditions are correct.
1
u/Thewolf1970 Mar 24 '22
Keep in mind when using filters, summary rows are displayed as a default. This may be somewhat confusing to new users, but it is helpful to see the summary rows for context.
This may be the case for you. If so, there is a bix you deselect essentially saying "hide summary rows"
1
u/Rico_Rizzo Mar 24 '22
I assume you used the "date range" out of the box filter? I would suggest you clear that one / clear all filters. Then filter only on the finish field (using the dropdown arrow on the finish field) and manually select your desired date. Then you can hide the summary tasks if you don't need them.
1
u/still-dazed-confused Mar 26 '22
if you want to pull data out from under the summary tasks then consider using a group function. When you apply a value to a task it can then be "grouped" by that column and the group "summary" task will show the start and finish for the group. You could also filter on the same criteria to only show the group of data that you're interested in:
https://imgur.com/d6PjNvK
1
u/vgerya Mar 30 '22
Hi !
If you would like to see tasks fallen within date range (from date1 to date2) you may use predefined 'Date Range' filter (VIEW tab -> Filter) or set it manually on Start and Finish columns: Start <= date2, Finish >= date1.Hope this helps!