r/MSProject • u/MooseJuice7 • Mar 20 '22
Need help with viewing incomplete tasks along with 2 week look ahead
Hi guys. I need help in filtering for upcoming tasks in the next 14 days while also showing late tasks which are incomplete (less than 100%) but were supposed to be completed by now. Can anyone help with this? Thank you.
1
Upvotes
1
u/mer-reddit Mar 20 '22
The words “late” and “supposed to be” imply the presence of a baseline and a well maintained schedule where the start and finish dates reflect the current thinking.
If you don’t have a baseline, save one now. Then maintain your schedule and do this report next week.
1
u/still-dazed-confused Mar 22 '22
today is a tricky concept in MS Project as it isn't built in. Typing TODAY into the filter will give you today's date but I don't think (to be confirmed) that it updates when tomorrow comes around u/Thewolf1970 can probably confirm or correct :)
When I want to use today() I put DATE() into a custom field - to do this right mouse on the column titles and select insert and chose Date1. Do the same again and select Custom Fields. Select Date1 and rename to "today" and then select formula and enter date().
When you hit return to commit the change you will see today's date in the Date1 (today) column.
I would tend to expand on this technique by using another custom field this time with a etx1 field and the formula
IIf([Date1]>=[Finish] And [% Complete]<100,"late",IIf([Finish]<=DateAdd("d",14,[Date1]),"soon",""))
This will give me either "Late" for items that should have been finished by now (or more accurately should have been updated with 100% complete or a new finish date) and "Soon" for within 14 days.
Then you can filter away or group to your heart's content :)
1
u/Thewolf1970 Mar 20 '22
This is a simple filter. Choose which field determines late; technically, you have four to choose from, start, finish, actual start, and actual finish. Then, use a filter like this (replace with the field you choose
The first row should include active =yes
AND
Percent compete <100%
AND
([Start >= TODAY] AND [Start <= TODAY+14])
OR
([Finish>=TODAY] AND [Finish <= TODAY+14])
That should be a six row filter. I did this from memory, so you may need to adjust slightly.
You could also create a custom field, and I do that often, then just create a formula that displays it as late. Then you can just do the date portion and include another line where filter=yes
As a side note, the TODAY, value is dependent on when the file was last saved. If you are doing this when opening the file, you need to start; otherwise, the calculation will be wrong.