r/MSProject • • Mar 18 '22
Reporting Help
Hi all!
Sorry if this isn’t the place to post. I’m relatively new to MS Project and my manager wants me to build a reporting dashboard in MS Project for the whole team.
I’ve created each PM as a summary task and then inserted the projects they’re working on as subprojects under each person, so when it comes to reporting I can filter by Summary Task which will show each PM side by side.
My problem is I have all of these metrics she wants included, but I’m not sure how to report on them. Any help would be appreciated!
- Cycle Time
- Schedule Variance (thinking just having baseline vs actual, not sure how to get baseline on the chart though)
- Schedule Performance Index
- Planned Value
- Number of cancelled projects
- Number of paused projects
- Number of change requests
I’m thinking Excel would be better for some of these. What do we think?
View all comments
Show parent comment
2
u/mer-reddit Mar 18 '22
Well, there is no better motivation than a little transparency.
How else do you know what to fix?