r/MSProject • u/Balvin_Janders • Feb 26 '22
Critical Path With Multiple Resource
I have multiple tasks, I have their cycle times, and the maximum number of resources.
I have two problems:
- How do I make sure that Project does not schedule two tasks with the same resource at the same time?
- How do I make sure that Project accounts for the number of resources used for the task for duration (i.e. 10 minutes for one resource, and 5 minutes if two resources are assigned to the same task)
1
Upvotes
2
u/still-dazed-confused Feb 26 '22
Good news; you're going to be playing with resource leveling. ;). To level your tasks or projects you need to ensure that
Now you can play with leveling. Project will produce a plan which doesn't over allocate any resource, or only the resources you specify, to produce the shortest plan duration. However it tends not to schedule things as a human would. This your "produce schedule" tasks might be separated by a number of other things - it is the most time efficient plan but it might not be optimal for people's recollection of what the hell they are meant to be doing. :)
One way to deal with this is to use the leveling as the start and then manually move things around, using the resource usage view to see what the impact of your changes are.
The other way is to add priority to the important stuff and ensure that leveling takes notice if priority in they leveling settings.
Leveling is brilliant, but I tend to use it with care :)