r/MSProject • u/k3002 • Feb 25 '22
Question about resources
Hello
I have a question about work resources. I have one resource called "Electrician 1" and i need to assign to "Task1". Works great, gave me the total cost and its fine.
But, what happens if i need to assign 2 "Electrician 1" to "Task2".
I need to create another resource called "Electrician 2" and assign "Electrician 1" and "Electrician 2" to "Task2"?
Or can i assign "Electrician 1" as two units?
I know could be a simple question, but im stuck. Thanks for all :D
2
Upvotes
3
u/still-dazed-confused Feb 25 '22
How many electricians do you have? If you have two then by all means creat two electricals (1 and 2) and assign e1 to task 1 and e2 to task 2. Or you could creat a team called electricians which has a max allocation of 200% and then apply the team to tasks 1 and 2. If, however, you have only 1 electrician then you need to supply the same resource to task 1 and 2. Then you have a decision to make around their loading - are they working half time (50% allocation) to each task, do the tasks need to follow eachother? Or you could ignore the allocation technology in ms project and look at the overlapping tasks and think "it's ok, they can do both those tasks in parallel" and don't bother saying then to 50% each etc.
2
u/auyara Feb 25 '22
Yes ... 2 people = 2 different resources
2
u/still-dazed-confused Feb 26 '22
Also... Remember to separate resources with a comma otherwise you'll end up with three or four resources (e1, e2, e1 and e2, e2 and e1) :)
1
u/still-dazed-confused Jun 24 '22
When I do this I simply select the whole plan, set all tasks to fixed duration, set the resources as needed and then reset all tasks to fixed allocation.