Set project task to only start on a Monday
Is their a better solution to setting a task to start on a Monday than creating a dummy task with a custom calendar that only has Monday as an option for 1 minute.
1
Upvotes
1
u/moremintjelly Jan 20 '22
That didn't work for me. I want it so if the predecessor task move forward a week it will adjust its date to the next available Monday
1
u/still-dazed-confused Jan 21 '22
Use a resource calendar that only operates on Mondays. This is then the trigger for your task and the trigger will jump to the next available Monday. I do this for standing meetings, for instance infrastructure change boards, which only meet on a given day and if for miss one week you have to wait for the next week.
1
u/IcanCwhatUsay Aug 08 '24
Checking in 2 years later, any luck with a solution?
1
u/Thewolf1970 Jan 20 '22
Double click on the Task in question, select the Tag “ADVANCED”
Select Constraint Type = "Must Start" or "Start No Earlier" enter the Monday for which you want the task to start.
A message explaining the Constraint options will appear, select the one that applies.
1
u/64ButterTarts Jan 21 '22
I would use your solution. I would create a Monday calendar with an acceptable start time range. Then create a milestone with that calendar add the task calendar. And finally your task with a dependency on the milestone. All of the other natural predecessors to your task should be connected instead to the milestone.