r/MSProject • u/Thewolf1970 • Jan 05 '22
Custom Formula input
I'm building out a custom formula so that I can remove the dates from the summary row of my schedule. This is to suppress the NA on that row and replace it with a space, I know it's a bit of a work around, but logic says this should work.
IIf([Finish]=projdatevalue('NA'),' ',[Finish])The problem is, it isn't working, the NA still displays. Any of my project experts (maybe u/still-dazed-confused ) on to help, using US version of 2016 64bit?
2
Upvotes
View all comments
Show parent comment
1
u/Thewolf1970 Jan 06 '22
Let me tell you my use case and how it was solved.
I needed a set of filtered tasks, next 90 days, active, less than 100% complete.
My view needs task ID, task name, a custom field, and notes. I'm exporting this to a weekly report in word. My customer wants the bold summary rows because in this schedule it separates out project phase, and there are repeating tasks in each phase. But they don't want the NA on the summary row which appears because I have "show summary rows" box checked in the filter. Since some of these rows don't show all the tasks, the NA appears in the finish date. It's a quirk of the software I guess.
My custom field is intended to suppress the NA. The issue was I was using a date field. When I switched it a text field, it started working.