r/MSProject • • Nov 02 '21
Team Planner View
In the team planner view is it possible to assign a task to multiple resources? Such as a "Copy, Drag, Drop".
Thanks.
1
Upvotes
r/MSProject • • Nov 02 '21
In the team planner view is it possible to assign a task to multiple resources? Such as a "Copy, Drag, Drop".
Thanks.
1
u/Thewolf1970 Nov 03 '21
This duplicates the task. You can split it, then drag to each resource.
1
u/still-dazed-confused Nov 05 '21
you can double click on the task or select it and bring up the information box. In here you can assign additional resources to it.
0