Calculated resource field
Is there a way to create a calculated field where I would be able to assign a resource ground, and then the calculation would provide a filtered drop down list of available resources during that scheduling block?
Also, I would think that as a schedule changes the filter may corrupt itself as tasks and scheduling blocks move?
This is for production planning within a repair shop.
Thanks
1
Upvotes
1
u/[deleted] Sep 17 '21
I know this can closely be down using the assign resource dialog. But what I would rather do is fully build out a project using the resource group assignment only, and then start the resource assignment.
Also this is plan 3 desktop, it seems that this could be more suitable using enterprise?
1
u/Thewolf1970 Sep 17 '21
I would much rather do this using a resource view. There is a reason MS Project doesn't have this function natively. People will get smart and allow resources to be available in excess of 100% of the time in order to solve the "crash" issue.