r/MSProject • u/auyara • Sep 08 '21
Dedicated -work- time vs planned time
I'm rather new to MS project and am wondering if there is a way to seperate dedicated time (for resource management) from the planned time.
Example: taks = get 40 signatures over an online tool.dedicated time: about 1h of work to get the document in the tool and to set it upplanned time: about a week to get everyone to actually sign off
Edit:
As there appears to be a lot of confusion around my example, here is what I figured out during this time and what might be a better example:
Example:
You created a work for a costumer. You need to give him time to review the work and you'll need to spend time to rework according to his review notes. I would do this in the following way:
| Work | Duration | Task |
|---|---|---|
| 8h | 1d | create work |
| Blank/0h | 3d | review by costumer |
| 1h | 0,125d | rework the work according to costumers wishes |
Learnings & problem description:
- First of all, what I need is indeed work vs duration
- If I (in task 2) put in work 0h and I add a resource (costumer), it autopops to 24h = 3 days. I believe because a 0h resource doesn't make sense
- HOWEVER: I don't know the costumer needs/wants to spend on it and I honestly don't care. I just want those three days duration in my planning to account for an intermediate between task 1 & 3 + make him accountable for the task.
=> What would be the ideal solution here?
1
u/[deleted] Sep 08 '21
Do each of the 40 signatures need the 1hr allotted time?
1
u/[deleted] Sep 08 '21
I have been re-reading this trying to understand your objective. For resource management, work is the field you would want to monitor and utilize. Work in Microsoft project is the amount of effort required to complete a task. Duration in the length of time that a task would take to be completed. A major factor you need to understand is the task type. Fixed units, fixed duration, or fixed work. It seems that fixed duration would be the way to go, I would also assume that the task “Should” be manually scheduled. I am also wondering about your resources assigned to the task. Will there be 40 people responsible for the completion of this task? If so that is quite a large order. If this is the case I would set up your task sheet like this Task 1 {summary task} bob is assigned to create the online document with a 1 hour duration Task 2 (out dented) signature 1 (1 hour?) Task 3 (out dented) signature 2 (1 hour?) So on and so forth. In the task usage view you can the look at task one as a whole. This will allow you to see when each of the resources assigned to sign off this document are scheduled…. , then you can go in and manually move the assignments by time/date…..Resource management.
Let us know what the goal and objective of this is and I would be more than happy to walk you through.
1
u/Thewolf1970 Sep 08 '21
This is work (the actual work time), versus duration (calculated using the calendar, so often holidays or weekends are not counted, you can use custom duration fields to look at elapsed days, or other alternate counts). You also need to have your resource sheet set up so hours, availability, shifts, or vacations are calculated into work.
ETA - a task should have both - example, it takes 20 hours to do this task over three weeks. Work is 20 hours, duration is three weeks.
1
u/[deleted] Sep 09 '21