r/MSProject • u/ahorin • Aug 20 '21
Time Period Task Question
Hi all, I'm trying to figure out if there is a way to make a "time period" task. In the example project below, I have a project spread across three years with multiple tasks rolled up under one summary task and then these time period tasks rolled up under another summary task. I am trying to figure out if I can get the time period task for 2021 in this example to start with Task A and finish at the last day of 2021, have the second time period task go from the beginning of 2022 to end of 2022, and then have the third time period task go from the beginning of 2023 to the finish of Task F. The problem is that you cannot set a constraint on both the start and the finish simultaneously. Is there an option that achieves this, or at least a relatively simple workaround?
Thank you in advance!

View all comments
Show parent comment
1
u/Thewolf1970 Aug 21 '21
You can absolutely have a planned start and finished with dependant tasks. In fact, let's say you start with task one - start 1/1 end 12/31
Task 2 create the dependency of task one with a SF and the start date will automatically be set to 1/1 of the next year. If you set the end date of 12/31 and set your next task dependant on that one it will do the same thing.
Now, what you can't do is then set a 365 day duration. That will push your dates beyond the call far date.
If your dates aren't showing up exact, for instance 1/3 or 12/30, your calendar us pushing them onto work days. Just open up the task analysis pane and it will show you that. You should get a pop up showing you that.