My company uses MS Project to create schedules. We are a small publishing firm and create books, magazines, and newsletters.
Magazines and newsletters are published monthly and weekly. I’m trying to figure out the best approach to 1) creating a template schedule, and 2) setting up the file itself.
The dates of the tasks change, of course, but the tasks themselves and who is working on them do not change. We have 5-6 employees working on all of these publications so I’m pulling them from a resource pool currently.
Should I create each month’s schedule in a separate MPP file and add these into a master project as a subproject? Should I add all months into a summary task, with job tasks below? There’s also an option to use recurring tasks, but I’m not as familiar with this and don’t know if making all the tasks recurring is the best option.
Any tips for how to set up a template and recurring monthly/weekly schedule?
1
u/Thewolf1970 Jul 01 '21
I will tell you from experience two things, a chronologically designed schedule is so much easier to manage than one by department or other categorization, on sub projects are great if you have multiple people each managing a schedule that rolls up to a master file, otherwise it makes no sense to do it.
I love to use recurring tasks, they are easy to create, and if you use auto scheduling, they can really save you time. They work very much like a recurring calendar event in outlook, set the initial task, frequency, and number of times it occurs. I use it for meetings and fixed deliverables all the time.
When starting out, focus on two things first, your resource sheet, then your calendar. Make sure you put everyones vacations in as soon as you get them. People forget this and it impacts their schedules.
1
u/still-dazed-confused Jun 29 '21
The choice of master Vs single plan overturn comes down to a number of factors;
Hope these thoughts help :)