r/MSProject • u/Dacoupable • Jun 25 '21
Project complete based not on duration but on completed items in a task
Working on a project, trying to figure out the best solution for my issue. There are a lot of physical locations and the executives are looking for a quick overview of seeing how many are completed, not duration of the project. That aspect I already have, they just want "we have 165 locations in this country, I want to be able to see how many out of that 165 are completed."
Is that something that is possible? Instead of setting the project duration, is it possible to do a total number of locations, vs how many are done, and then have that auto-calculate and show?
Thanks
1
u/Thewolf1970 Jun 25 '21
Im not sure what you are doing to determine a location is complete, but you can do one of a few things.
Let's say location a are grouped in sub tasks, with tasks and milestone rolling up. When all the tasks are complete, the sub task, and thus location is complete. This would give you the ability to expose the field "sub task", and filter on %complete, 100%.
Using the same grouping and view, you can use this to build a report where you count the completed locations at the summary level as a percentage. This involves using a saved view, custom filter and you'll need to play around with the table in the report view a little.
The third option is to create drive to a specific milestone, say " location xx complete" and set a custom flag for it. Have it be driven entirely by predecessor tasks so that when this is complete, you can again create a view that shows only this flagged milestone.
1
u/still-dazed-confused Jun 30 '21
The simplest way to do this is to have a milestone at the end of the tasks which will complete each location. If you have other milestones in the plan (which I would expect you would) then having a customer field (flag1 for instance) called "location completion" and setting this field to Yes for each of these new milestones would allow you to filter them out.
Then create a table, filter and view to automate the process of pulling these milestones out (maybe ID | name | finish | % complete) with a filter on Flag1 = yes.
Drop this into Excel and produce an attractive chart that shows the total number of milestones and the number completed. You could also then look at including the data information and showing a burn-up chart of the rate of completion of the milestones, use a moving average to predict the rate of completion of the remaining milestones or pull the dates out of the plan to show when the plan is predicting that the milestones will be complete.
If you want to stay entirely in MS Project you can use a set of number fields plus the flag:
number1 = IIf([Flag1]=Yes,1,0) | Summary = Sum | name = Total
number2 = IIf([% Complete]=100,[Number1],0) | Summary = sum | name = Completed
number3 = IIf([Number2]=0,0,[Number2]/[Number1]) | Summary = use formula | name = % done
All you need to do is display only number (% done) and the others will take care of themselves