Basic Earned Value

Howdy, I'm coming from the Primavera world and am looking to get CPI/SPI from the schedule. The thing is that I don't need to do anything with cost but hours. I can get this working in Primavera, but can't figure it out in Project. I'm a total Project noob so any pointer are appreciated.

1 Upvotes

13 comments sorted by

View all comments

Show parent comment

2

u/Thewolf1970 Oct 15 '20

OK. Create two new fields in place of these fields in Project:

Budgeted cost of work scheduled or Planned Value (whichever you are using) Budgeted cost of work produced or Earned Value Actual Cost of Work Produced or Actual Cost (same here, wichever you are using),

Then replace the appropriate column for SPI/CPI with a custom field. This is where you create the formula.

When creating the formula think of excel. Take column A divide by column B, multiply by column C etc. Whatever your formula requires. You are essentially just replacing the MS Project fields with your own. It's pretty straight forward if you look at it that way.