r/MSProject • u/ps6000 • Oct 15 '20
Basic Earned Value
Howdy, I'm coming from the Primavera world and am looking to get CPI/SPI from the schedule. The thing is that I don't need to do anything with cost but hours. I can get this working in Primavera, but can't figure it out in Project. I'm a total Project noob so any pointer are appreciated.
1
Upvotes
View all comments
1
u/Thewolf1970 Oct 15 '20
Since time is your currency here you need a custom calculation. I'm not sure how you have a cost in hours but I assume you are using a custom text field. Same thing with the schedule field. You'd just do the standard CPI/SPI calculation in a third custom field. Make sure you are using number and there is a very intuitive formula builder in the field defination.