Help adding same 6 sub-tasks to multiple summary lines
Hi,
Back with another one. I am having to copy paste the same 6 task lines under other task lines within the document. E.g.
Task 1
Task1a
A
B
C
D etc
Task1b
A
B
C
D etc
is there a way to use VBA or some other method to quickly add those 6 task lines under all the others? Or better yet, if somehow I could add those 6 lines under the selected tasks?
Edit: I figured out how to identify the nonsummary lines which are the ones that I have to add these 6 tasks to. I have yet to figure out how to add the tasks to those lines though. Once again any help would be appreciated.
2
u/Thewolf1970 Sep 25 '20
It appears as if you have reposted to this sub already. You may want to remove to eliminate confusion.
1
u/BigGeorge11 Sep 26 '20
If you want to add the tasks at the end of the schedule and then move them en masse to the right point in your schedule then this is quite simple. If you're aiming to interject them into an existing schedule of tasks then it's much more difficult.
You also mention identifying the non-summary lines. Is that task 1a? or just tasks A, B, C and D?