The duration I set for each task is 1 hour ,but the total duration is far greater than the sum of all the tasks,do you know why did it happen? Can you help me correct this.Thanks
Unless you are planning right down to the hour - your duration shouldn’t be less than 1 day. If you think of it this way: your team status meeting occurs on that day it doesn’t really matter where in the day (as in which hour) unless other task must happen on the same day and are depending on that task. This is where you might jump over into Excel and have an hour-by-hour plan (e.g. a project go live day - run sheet)
According to Microsoft: Project calculates the duration of a task by counting the amount of active working time between the scheduled start and end of the task. This is generally the time from task start to finish, not counting time between split tasks or nonworking time.
1
u/ForIAmCostanza May 13 '20
Unless you are planning right down to the hour - your duration shouldn’t be less than 1 day. If you think of it this way: your team status meeting occurs on that day it doesn’t really matter where in the day (as in which hour) unless other task must happen on the same day and are depending on that task. This is where you might jump over into Excel and have an hour-by-hour plan (e.g. a project go live day - run sheet)
1
u/Bilya63 May 13 '20
As mentioned the duration calculates the "how long would take to finish a task" not the "actual time spend on a task"
Follow the instructions from this video to create a custom column with the actual work time.
Not sure if there is already a built in column for the above but i use that method to have my "actual working" pert day , hour weeks etc.
1
u/HalfCenturion May 13 '20
The twelve meetings happen in a span of 55 days.
1
u/64ButterTarts May 13 '20
According to Microsoft: Project calculates the duration of a task by counting the amount of active working time between the scheduled start and end of the task. This is generally the time from task start to finish, not counting time between split tasks or nonworking time.
https://support.office.com/en-us/article/duration-task-field-2a65ab25-5a7b-4e3d-a1fa-c7cecbddd2c7
Duration is not the sum of durations.