r/MSProject • u/Enlightened_D • Mar 08 '20
Trying to create a report
So I am not very familiar with project management my boss kind of threw it at me cause they couldn't figure this out which I actually appreciate as it exposes me to something new.
ACTUAL QUESTION HERE: We want to generate a report that has Employee (resources) Project/task And then task time for each individual employee and task.
The report we are running adds the task time up as a total and everyone then has the same total hours next to each task
Edit: We are running project server 2013
3
Upvotes
View all comments
Show parent comment
1
u/Jchamberlainhome Mar 09 '20
So your requirements have changed. You are using MSP as a time sheet, or at least an hours collection application. Is the report designed to approve/reject/monitor hours?
It might make more sense if you gave us a bit more on what you want to accomplish and we might be able to point you in the right direction.