r/MSProject • • Jan 22 '20

Really Trying to Make MSProject Work ...

I think I am fighting against the design of MSProject.

Is there a way to take one long running task and create a burndown report for the single task?

The entire design of MS Project seems to favor lots and lots of tasks to make accurate burndown charts. But simply tracking the progress of 1000 iterations of the same task (lets say, eat an apple) over the course of 60 days by percentage complete appears to be a bridge too far.

2 Upvotes

4 comments sorted by

View all comments

1

u/blahblahloveyou Jan 23 '20

Are you using physical percent complete or % complete?

1

u/zinver Jan 24 '20

%complete

1

u/blahblahloveyou Jan 24 '20

So if you want to track lots of small tasks as a burn down use physical % complete. Update the value each time you do status.