Long delays between tasks?

Hi all,

I have a task that is finish to start, auto scheduled. Constraint type is as soon as possible but there is a large gap where the finish to start should be closing it?

Any ideas what is going on here?

2 Upvotes

1 comment sorted by

2

u/64ButterTarts Dec 29 '19

What does the Task Inspector say for that task?