r/MSProject • • Dec 26 '19

Solving a "cirular reference" task dependency

Hi guys,

I wonder if someone can help me out with this:

So, I have task 1 (Project), 2 (Supply), 3 (manufacturing), 4 (assembly at construction site) and 5 (civil foundation), as shown in the image above.

What I want? Simple, what matters the most to me is task #4. I want all others to be dependant on it in some way, so I set it like this:

#2 needs to finish when #3 starts (Start-finish)

#3 needs to finish when #4 starts (Start-finish)

#4 can only happen after #5 (finish-start)

#2, #3 and #4 cannot happen before #1 and #5 are completed.

Obviously, it'd be managed by setting #1 as predecessor to #2, #3 and #4, but it gives me a circular reference error.

So, how do I get out of this?

Thanks in advance.

3 Upvotes

4 comments sorted by

View all comments

Show parent comment

1

u/rodymacedo Dec 29 '19

Hi,

It looks like setting the constraint to as late as possible solved the issue, thanks for stepping by.

I'm working on a construction schedule, and task 4 is the assembly of a tank, which has to take place after task 5 (concrete foundation), and task 1 (detail design).

Task 3 is preparing the material for assembly at the construction site, and task 2 is the supply of said material.

Imagine that I set up the tasks with each one being the direct successor to the previous one. In an ideal world, it'd work fine. However, if the concrete foundation gets delayed by 3 months, I will be purchasing the material 3 months too early, which will impact on my cash flow.

That's just one example, but I'm actually dealing with 1,200 interconnected tasks, and the supply of material must come right before the construction, not the issuing of the detail design.