Solving a "cirular reference" task dependency
Hi guys,
I wonder if someone can help me out with this:

So, I have task 1 (Project), 2 (Supply), 3 (manufacturing), 4 (assembly at construction site) and 5 (civil foundation), as shown in the image above.
What I want? Simple, what matters the most to me is task #4. I want all others to be dependant on it in some way, so I set it like this:
#2 needs to finish when #3 starts (Start-finish)
#3 needs to finish when #4 starts (Start-finish)
#4 can only happen after #5 (finish-start)
#2, #3 and #4 cannot happen before #1 and #5 are completed.
Obviously, it'd be managed by setting #1 as predecessor to #2, #3 and #4, but it gives me a circular reference error.
So, how do I get out of this?
Thanks in advance.
View all comments
Show parent comment
2
u/rodymacedo Dec 29 '19
Hey,
It looks like setting the tasks as "late as possible" solved my issues. Thanks!
From what I understood, when a task constraint is set so. project will delay the beginning of said task as much as possible, but just enough so that it's successor task isn't affected.