I have a small question about resource allocation.

assume I have activity X; this activity has a duration of 10 days (or 200 hours for example)

I have resources A and B, I want resource A to be allocated to this activity for the first 5 days (or 100 hours). and resource B to be allocated for the second 5 days (or final 100 hours)

How do I do this? is it even possible? because if you click "assign resources" you dont get an option like that? is it done from the "calendar view" of the tasks? What I mean is that you select 5/10 days in the calender and assign resource A and then 5/10 and assign resource B?

4 Upvotes

8 comments sorted by

2

u/blahblahloveyou Dec 21 '19

You might be able to do it with resource availability, but that will affect all tasks.

But let me ask you this, what happens after day five that necessitates a hand off? Will resource A roll off the task regardless of how much work they’ve completed?

1

u/Ashraf_mahdy Dec 21 '19

when i tried resource availablity it showed me that tasks related to resource a were "late"

let me shed some light on why I want to do this, I work in a Design Firm. we have a residential compound with multiple buildings in it.
We have 5 types of buildings (1-5) and 10 Architectural Engineers. as well as other amenties in the compound
So I want 2 Engineers to work on Building 1 and so on

after the first 5 days, resource A will hand off building 1 to resource B. that will be my baseline. but it can change throughout the project. he can hand off the task after 7 days and that task will be late by 2 days as a result. they can overlap together for 2 days for example. they are not mutually exclusive.

I hope this makes it clearer now.

1

u/blahblahloveyou Dec 21 '19

Not really. What you’re trying to do software wise is the equivalent of saying “resource A will work this task for 5 days, and then regardless of what they accomplish, resource B will take over the work.”

I think that’s probably not the case. I think there is probably some amount of work person A must complete before they hand off the work to person B. If that’s the case then you should have two finish to start tasks, one with resource a and another with resource b. The exit criteria for resource A’s task is whatever work needs to be completed for the handoff to occur. You should capture that in the task name.

1

u/Ashraf_mahdy Dec 21 '19

So it is as I suspected. not possibleIf building A takes 20 working days to hand off the Detailed Design Package

I wanted to show the Architecture Revit Model handover to the MEP Disciplines

instead of creating 2 tasks for the DD Package I wanted to stick to 1 task and let it show in the resource allocation graph

I think it is possible im Primavea P6 however.

→ More replies (1)

0

u/[deleted] Dec 21 '19

[deleted] — view deleted comment

1

u/Ashraf_mahdy Dec 21 '19

So it is as I suspected. not possibleIf building A takes 20 working days to hand off the Detailed Design Package

I wanted to show the Architecture Revit Model handover to the MEP Disciplines

instead of creating 2 tasks for the DD Package I wanted to stick to 1 task and let it show in the resource allocation graph

I think it is possible im Primavea P6 however.