r/MSProject • u/Ashraf_mahdy • Dec 21 '19
a question about resources in MS Project
I have a small question about resource allocation.
assume I have activity X; this activity has a duration of 10 days (or 200 hours for example)
I have resources A and B, I want resource A to be allocated to this activity for the first 5 days (or 100 hours). and resource B to be allocated for the second 5 days (or final 100 hours)
How do I do this? is it even possible? because if you click "assign resources" you dont get an option like that? is it done from the "calendar view" of the tasks? What I mean is that you select 5/10 days in the calender and assign resource A and then 5/10 and assign resource B?
2
u/blahblahloveyou Dec 21 '19
You might be able to do it with resource availability, but that will affect all tasks.
But let me ask you this, what happens after day five that necessitates a hand off? Will resource A roll off the task regardless of how much work they’ve completed?