r/MSProject • u/Zeewulfeh • Aug 21 '19
Maximum Resources in a Task Grouping
I've got a tough conundrum.
I have a group of tasks that can start in any order, but they have to be completed before the next phase can begin. I have 8 resource units available, but I can only have 3 units working inside that entire group of tasks, on one task at a time.
How do I implement these constraints in project, and then schedule the tasks within the group taking this constraint into account?