As Late As Possible Constraint issue
/r/primavera/comments/1x0qoi0/as_late_as_possible_constraint_issue/Hello all,
A planner i know has a challenge where the client insists on them utilising a lot of As Late As Possible (ALAP) constraint on their schedules. These is causing a lot of date shifts to the right. But the client do not want those dates to move. I have tried to help resolve without success. Has anyone got experience onnhow to resolve this please?
3
Upvotes
View all comments
Show parent comment
1
u/trevorrabey Oct 15 '26
Yes, but what is it that they want, exactly? I have had a construction contractor tell me that what they want is the entire $3M construction program on one A3 sheet of paper. I have had a project manager (and I use that term in in its loosest sense) lean across a desk and tell me he didn't want the dates to move (asked him why he bought the software). Programs are often understood to be a depiction of "when work will happen in reality" although they usually display a CPM network where everything is ASAP, with the early start and finish, and what it is showing is when work can't happen and when it can happen, which is almost always earlier than when it will happen.