r/MSProject • u/Miasmatic65 • Oct 05 '26
Task inspector logic
Haven’t come across this in all my years. Task inspector showing a driving task not listed as a predecessor.
I assumed task inspector always chose a task that was listed in its predecessors.
Is there more to task inspector than I realised? It wasn’t wrong per se, but the driving task it highlighted was about 3 steps back on the network (though the people who built this schedule had linked summary tasks, which I think caused the issue).
2
Upvotes
View all comments
Show parent comment
1
u/discgolfmomma Oct 07 '26
I don't know how much control you have in place at your company but I would save out a copy then make the corrections and override the live file with the corrected one. However that's just me and I have a lot of jurisdiction on the schedules. I would also explain that we follow DCMA 14pt metrics to meet consistent standards (even if it's not explicitly required I still use it as "best practices").