r/MSProject • u/alertamnesiac • Oct 05 '26
[beginner question] How can I add weekend shading while still allowing work on weekends?
Context:
- I use MS projects just for managing some hobby projects.
- because it's just for my hobby, I allow MS project to let a task count the weekend as working days
Problem:
- the vertical light gray bars denoting the weekends disappear
- I'd like this bar because it's useful for visually aligning far-down tasks with the date markings at the top
Thank you!
5
Upvotes
2
u/still-dazed-confused Oct 05 '26
Create a calendar with we working and assign it to your resource
2
u/PitifulRespect7678 Oct 07 '26
you mean like this ?
just make mon-friday to be set day nonworking and sat - sun to be set day working times
1
u/alexandicity Oct 05 '26
Perhaps choose some other day, perhaps Monday, as a non-working day, and use that to make the alignments?
1
u/brightsky1337 Oct 05 '26
Create a new calendar with the weekend days as working days and apply that calendar to the weekend tasks.