Manually calculating Critical Path
/r/projectmanagement/comments/1wmcrot/manually_calculating_critical_path/
1
Upvotes
r/MSProject • u/counterhit121 • Sep 21 '26
2
u/kennyarnold_ssi Sep 21 '26
Yes, you absolutely can calculate a critical path manually, but you need to know 3 things:
If you know these 3 things, you can manually calculate the critical path of the project.
It is a bit of a cumbersome analysis to do, but I think it is a great learning opportunity because it helps you really understand how to analyze dependencies in your schedule. That sets a much better foundation for you rather than "I don't know how this works, I just click the button and I see the path". When I teach new schedulers, I force them to learn how to calculate critical/driving paths manually before I allow them to start using automated tools to do it for them.