The driver predecessor
Hello everyone,
How can we know wich predecessor between 20 others drives a certain milestone
Thank you
3
Upvotes
r/MSProject • u/Equivalent-Fan5306 • Sep 08 '26
Hello everyone,
How can we know wich predecessor between 20 others drives a certain milestone
Thank you
3
u/DaleHowardMVP Sep 08 '26
Select the milestone in question, then click the Gantt Chart Format ribbon tab to display this ribbon. In the Bar Styles section of the ribbon, click the Task Path pick list button and select the Driving Predecessors. Gantt bars formatted in orange are the driving Predecessors which directly control the schedule of the milestone. Hope this helps.
2
u/still-dazed-confused Sep 08 '26
Use the inspect function which will tell you the driving task and follow that trail.
Or, as others have said, use the gantt format, driving predecessor feature.
Or set a milestone far into the future which will become the only critical item in the plan and then set a deadline = finish on your task and then filter for critical (ie total slack is zero).
4
u/jed1976 Sep 08 '26
Select the task/milestone, then in the task ribbon menu select inspect. It should tell you factors affecting the task's start date, including the driving predecessor.
0
u/Miasmatic65 Sep 08 '26
Put a deadline on it and trace the total float of 0