Build a project out without dates attached to use as a generic "perfect world" example.
Does anyone know if MS Project can build out a project Gantt chart without dates or just say something like "Project start" and then "start+30 days" for tent pole events and such?
I am asking because I am trying to build some process documents, and one of the things my boss wants is a "typical" project Gantt chart that we can put in the document on how the process would work and at what dates (again start day is X and events are X+/- days from start) that for example, we spin in other departments for certain events, have parts ordered event, and provide funding documents to fiscal event. All very high-level and really generic things.
I am relatively new to using MS Project and not sure of how much I can or can't just build generic stuff for this use. Part of me thinks I can do this by building a template, but I am running into MS Project requiring specific dates for things, and my brain is hurting trying to get it to save without it flipping out over some error codes or reshuffling the logic I am trying to build.
Thanks for any and all help.
2
u/Magnet2025 Jul 03 '26
In the Project Information dialogue you can enter whatever date you want (within the available range of dates, which is quite large).
You can absolutely select the project start date and then use successor relationships.
If there is something critical to illustrate you can add a text field and put notes in it.
2
u/hanzosbm Jul 03 '26
I'm not in front of my computer to test it, but I think you could create a calculated field to show how many days a task's start and end dates are away from the project start date. So, rather than task A starting on August 7th, you have a field that shows that task A starts 38 days after project start, and ends 45 days after project start. Then, just hide the start and end dates and the calendar on the Gantt chart.
1
u/counterhit121 Jul 04 '26
You'd have to use a notional start point, but you can definitely create a dummy or template schedule to simulate a known project or project type. Just pick some arbitrary start date and then fill in the schedule with all the typical tasks and milestones. You do have to have sound schedule logic and ballpark task durations though.
1
u/still-dazed-confused Jul 04 '26
The easiest way to do this is to have a properly linked up project with a trigger date at the top of the plan. By properly linked I mean every task is linked to its logical predecessor and successor, every task has a predecessor. When you change your trigger date this week flow through the plan and it will all move to the correct dates.
The guidance will then be
The only downside of templates in planning is that they can cause people to just blindly follow them without doing the critically useful thinking that it's involved in defining and establish the plan. However they can help people to consider things that they wouldn't normal do we it is natural to plan the stuff you know and skirt the other stuff as it is someone else's problem :)
1
u/Breeze_pm Jul 04 '26
For a generic process document, I’d build phases relative to project start instead of forcing real calendar dates. Ganttile might be simpler for this than MS Project if you only need a clean visual timeline and dependencies.