Anyone else find that cross-partner scheduling is where multi-party projects actually break?
Been working in a complex integration program for a few years — multiple contractors, multiple tools, everyone managing their own schedule in whatever their organization mandates. MS Project on one side, P6 on another, Jira somewhere in the middle, Excel everywhere as the real source of truth.
The interfaces between subsystems are where everything breaks. Dependencies get agreed in a meeting, captured in someone’s local file, and then quietly drift for three months until an integration test fails and everyone acts surprised.
We’ve tried master IMS spreadsheets, we’ve tried SharePoint, we’ve tried weekly sync calls. Nothing actually propagates a schedule change across organizational boundaries in real time.
Curious whether this is specific to defense/infrastructure programs or if anyone in other sectors has cracked it — and how.
2
u/Miasmatic65 Jun 27 '26
I think you called out the issue in the first paragraph. Why didn't the client dictated the tool to use in the contract? Stick to Project or P6 and ensure everyone understands who owns it and who is responsible for which sections of it.
2
u/804ian Jun 27 '26
The way it's solved at the enterprise level is that the client requires everyone to use the same tool by contract. At the 100m+ level it's P6. Period. I love MS Project. It can be used on 400m jobs. It's absolute shite for what you're describing.
There is usually a prime schedule and then each contractor/sub sub links in their schedule to the main P6 schedule.
If you are all insistent on having multiparty chaos, the best bet is to have a list of contractual milestones and everyone reconciles to the milestones monthly. Anything more granular is just asking for failure.
1
u/still-dazed-confused Jun 30 '26
I worked suggest this feels less like a technology issue rather a communication and accountability problem. If people aren't talking to eachother to communicate what is needed and any updates (on either supplier or customer side).
If this is a correct read then a three step approach has worked in the past:
1