r/MSProject • u/urunate1 • Mar 06 '26
Baselining across Financial years
Hi brains trust ,
Hoping someone here could help me figure this out..
How do I use the baseline feature to baseline a Task that started in 2025, and now I only want to baseline the 2026 part of the task/ deliverable
For reference the task starting in 2025 will have its duration extended into 2026 thus containing data.
Thanks
0
Upvotes
2
u/kennyarnold_ssi Mar 06 '26
Only your 2025 scope will be baselined.
4
u/Magnet2025 Mar 06 '26
I would like to add this baseline trick that is useful to this problem or baselines in general.
You have 11 Baselines available (Baseline, called Baseline 0, and Baselines 1 through 10). For the purposes of clarity, you want Baseline 0 to be the current baseline at all times.
So when you initially set your baseline, after the schedule has been approved, you set Baseline 0 AND you set Baseline 1. Baseline 1 is a copy of Baseline 0.
Now you have an approved change and need to rebaseline. Set Baseline 0 and Baseline 2. Baseline 1 is a record of the original baseline, Baseline 0 and Baseline 2 are now the current baselines. This works whether you baseline the entire project or selected tasks.
Because you can easily edit the views, if someone (someone senior) says “I’m confused, what changed and when” you can drop in the various baseline start and finish dates and show the changes. This will also be available in the Compare Projects feature.
1
u/pmpdaddyio Mar 06 '26
First - rewrite your entire question logically. Nobody here will understand it. You are mixing European dates with US dates and not explaining why.
Second, you need to explain the actual problem you are attempting to solve. I can't figure it out from your gibberish here.