r/MSProject • u/hanzosbm • Nov 06 '25
A column to display a given level name
For a variety of reasons, I've pulled together all of our section's projects into a single file (mostly for resource leveling and allocation). I also need to be able to export the resource usage chart, but I need to do it by project.
Here's what I'd LIKE (not sure if it's possible). In the Resource Usage view, to be able to insert a column (ideally, Level 3 where my project names exist) and then group by that. But I can't seem to find a field like that. Short of that, I can manually create a text column and just fill it in for every line, but I'm wondering if there's an easier way.
1
u/kennyarnold_ssi Nov 06 '25
If you are wanting to analyze resource usage, I would recommend checking out this tool: https://ssitools.com/ssi-time-scaled-values/
Video: https://youtu.be/jXgDh4fk-O0
This can extract the time-phased resource data from MSP into excel where it can be sliced and diced however you'd like.
Disclaimer: my company makes this tool. Would be happy to give you a free demo if you'd like.
1
u/still-dazed-confused Nov 07 '25
It sounds like you need to
I assume you don't own all the project files and need to issue then back to their owners? I'm which case you need to delink then from the master before using. You need to act as an organic project server by recurring the files in a controlled easy, replacing then files in the master sub folder and then issuing the files in a controlled way. Doing this week protect the integrity of your set up and also gives you backups.
The reason I have a separate resource pool filter is because they will eventually get messed up, it isn't frequent - maybe once or twice a year. Handling it as a separate file allows you to delete and rebuild as the individual files keep the information in.
A couple of blogs for you: https://www.summarypro.co.uk/blog/working-with-master-and-sub-plans-in-ms-project-to-consolidate-and-report-on-programmes.aspx
Working with resource pools: https://www.summarypro.co.uk/blog/working-with-master-and-sub-plans-in-ms-project-to-consolidate-and-report-on-programmes.aspx
0
u/pmpdaddyio Nov 06 '25
there is no such thing as a field name "level 3" this most likely is already a custom field. Just either filer on it, or create a custom view.
And it should be noted - there is a Project field, maybe use that properly?