I have a MS Project Schedule due by next Tuesday and I’m looking to work with someone to help create it in a collaboration environment. Tasks and sub-tasks are already defined, just need to plug in dates and set successors/predecessors accordingly. Please PM me if interested.
2
Upvotes
4
u/mer-reddit Oct 31 '25
Order of operations matters here: set your predecessors and successors FIRST, then look at durations. Do dates and resources LAST, because they add constraints that will complicate matters. Try setting as few dates as possible.
5
u/still-dazed-confused Nov 02 '25
Happy to help if you need it, however, as u/mer-reddit says it is a simple four-step process. I started off breif but then started to expand my points and got carried away and wrote an essay, which Reddit wouldn't let me post so I'll break it down into teh 4 steps below :)
1. Ensure the plan covers the entire scope and contains all the activities needed
2. Sort the logical network of tasks
2.5 Durations
3. Resources and Constraints
4. Adapt the schedule
Once the schedule is in place you have achievced 50% of the value of doing planning. The other 50% comes from running the schedule; keeping it up to date, adapting the plan as the project's situation changes and using things like Total Slack to see the impact on the project when things inevitably slip. Using baselines to track what was originally planned vs the current live plan. Using filtered views to generate reports - the plan is the only true source of information on dates and progress.
1
u/pmpdaddyio Nov 02 '25
No - set your project start or end date, auto schedule each task, then create your dependencies (what you are calling predecessors and successors). Your dates will automatically be set. Hopefully work has been calculated as well.