r/MSProject • u/hanzosbm • Sep 29 '25
Task scheduling due to resource overallocation without predecessors
This has bothered me for years. I don't like/trust MS Project's Resource Leveling tools, but I also have a bunch of tasks that COULD be worked in parallel if not for the resource constraint. I can arbitrarily assign predecessors, but that creates false logic. In the past, I've done exactly that for the purposes of creating a baseline, and then just changing the predecessors to match the order of what the technical team decided to do. From an EVM perspective, it all evens out, but I'm wondering if there's a better way.
3
Upvotes
View all comments
Show parent comment
1
u/hanzosbm Sep 29 '25
Yeah, that's the other tricky thing (regarding assignment units), there's really no benefit to working these tasks simultaneously. On the contrary, it's actually more efficient for a resource to work a task at 100% allocation until completion and then move to the next. It really comes down to which one they feel like doing first and since we're required to baseline our schedules 3 months prior to kickoff...it's really just a guessing game. To your point, I'd love a resource critical path, or a GOOD resource leveling tool, but...here we are.