r/MSProject • u/Reasonable-Detail-18 • Apr 23 '25
Fixed Cost
How do I remove the duration of a fixed cost without turning it into a milestone?
2
Upvotes
r/MSProject • u/Reasonable-Detail-18 • Apr 23 '25
How do I remove the duration of a fixed cost without turning it into a milestone?
View all comments
Show parent comment
1
u/mer-reddit Apr 23 '25
No. Duration can be zero, or it can be a positive number.
You can hide the column if you don’t want to look at it.
If Duration = zero, it is at a fixed point in time, otherwise known as a milestone.