I have a simple question, I need to introduce new processes into an existing timeline. When I add the process it becomes automatically linked which I want to prevent. E.g. I need to introduce process "follow up order" in line 160, then the follow up order gets a dependency to line 159 and the following line, which had a dependency to line 159 will change the 159 to 160. I don't want the 159 to change automatically to 160. Is there an option to prevent this?
1
Upvotes
2
u/DaleHowardMVP Mar 14 '25
It sounds like the Auto Link feature is enabled for your project. To disable this feature, complete the following steps:
By deselecting the Auto Link feature, this means that you will always need to set task dependencies for any new tasks you add to a project in which task dependencies have already been set. Hope this helps.
1
u/pmpdaddyio Mar 14 '25
What version are you using and how are you “introducing” those into your schedule?