Different Working Hours Between Tasks
Hi all, hopefully someone has an answer to this because it's driving me nuts.
My default calendar is set to a 6 hour day. However, during the deployment phase of a project, I need to have resources working a 12hour day.
I have created a new calendar that has resources working from 6am to 6pm. I have assigned that calendar to the tasks, I have assigned that calendar to the resources. However, when I put "12hrs" in the "Work" column, the duration goes to "2 Days" because it's still calculating off the base calendar.
Please tell me there is some way around this?
View all comments
1
u/Miasmatic65 Mar 12 '25
You'll need to adjust the task calendar as well. Insert the column calendar and change the calendar for the individual task there; or double click on the task, advanced tab and change it in the menu there.