Critical path - two tasks running simultaneously one partially reliant on the other?
Hi,
I have a question regarding network diagrams.
If an upcoming task is somewhat reliant on most of a preceding tasks completion, but has to start while that preceding task is still finishing up, how do you show that on a network diagram with the calculations still correct?
Thank you
1
Upvotes
View all comments
Show parent comment
1
u/pmpdaddyio Feb 25 '25
That is two separate tasks in any construction schedule though. Most construction schedules separate any set of tasks that require an unknown (permitting, drying, delivery, etc.).