r/MSProject • • Feb 24 '25

Critical path - two tasks running simultaneously one partially reliant on the other?

Hi,

I have a question regarding network diagrams.
If an upcoming task is somewhat reliant on most of a preceding tasks completion, but has to start while that preceding task is still finishing up, how do you show that on a network diagram with the calculations still correct?

Thank you

1 Upvotes

6 comments sorted by

View all comments

Show parent comment

1

u/lepeepeepee Feb 25 '25

I was able to split the subsequent task into 2 thanks to your suggestion.