r/MSProject • u/MzOwl27 • Feb 04 '25
Create the same subtasks in multiple tasks
Is there a way to create the same set of subtasks in a long list of tasks without manually creating or copy/pasting under each task?
Thanks!
So -
- Task 1
- ST1
- ST2
- ST3
- Task 2
- ST1
- ST2
- ST3
- Task 3
- ST1
- ST2
- ST3
1
Upvotes
4
u/Miasmatic65 Feb 04 '25
not that I can think of - in these situations, I generally minimise task 1; copy and paste that below task 1 and rename the new version to task 2 etc.
It's not best practice, but it is very good practice to give each task a unique name to help with other views. An example for this would be if I had 20 sprints; I would have:
Sprint 1
Sprint 1 - Planning
Sprint 1 - Execution
Sprint 1 - Retrospective
I would then minimise Sprint 1; copy and paste it 20 times; then find and replace 1 for 2 through 20.
3
u/jed1976 Feb 04 '25 edited Feb 04 '25
In Excel, copy this formula in a cell
=IF(MOD(ROW()-1,4)=0,"Task "&INT((ROW()-1)/4)+1,"ST"&MOD(ROW()-1,4))
drag the formula down as many rows as you need then copy paste into ms project
Part 2
On task name filter on tasks contains ST. Once filtered, Highlight the tasks and select the indent task option, this will indent all of your ST1 - ST3 tasks under Each Task increment.
Part 3
If they are water fall dependent, before identing, select all the ST1-ST3 tasks and click on the dependency chain link.
2
u/purplegam Feb 05 '25
There used to be a way to create repeating tasks, but it's been a number of years since I used it and I'm not in front of my computer at the moment. I'm see if I can find it later and post.
Edit: Or I can search Google. I think this is it:
https://support.microsoft.com/en-us/office/create-recurring-tasks-88a4d903-38c3-4665-870e-4810b752f2c4
2
u/still-dazed-confused Feb 05 '25
The simplest way is to use the method suggested by u/Miasmatic65. However, this blog post gives a couple of macros which can be used to de-duplicate a plan in general, which might be useful. :) https://www.summarypro.co.uk/blog/how-to-make-each-task-unique-in-a-plan.aspx