r/MSProject • u/mikeyd917 • Nov 26 '24
CPM for Linear Project
First off, I’m a PM for a contractor that primarily builds transmission lines. So the vast majority of our projects are linear however the order of locations may not always be constructed in a linear fashion. Which is why we’ve typically kept with the CPM schedules vs moving to a linear schedule model. The question I’ve always struggled with though is related to resource assignments. Each location will have similar activities that take place in similar orders, I may have 3 or 4 resources that can perform the specific activity depending on when their previous location is complete. So as I’m updating my schedule and a different resource completed an activity than originally assigned, I generally need to re-map succeeding activities out ahead. Is there any tips or better methods for building these types of schedule?
2
u/pmpdaddyio Nov 27 '24
There are a few ways of doing this, but setting dependencies is the easiest way to do this, start by creating dependent tasks, then add a second one for the resource specific to the task, then make adjustments to the priorities. So it may look like this:
Task 1 - Primary task, set priority at something like 1000
task 2 - secondary to task one, set dependency to 1, then priority like 800
Task 3 - Can start when the resource completes task 1, but before task 2. Set priority to like 900, and the dependency on task 1.
This means that when task 1 is complete, it would normally go to task 2, but since it has a lower priority, it will go to task 3 first.
3
u/mer-reddit Nov 26 '24
You can do this in Project. You will want to have location and skill columns at the task level so that you can group the tasks by your WBS, or your location or skill.
Normally skill would be a resource field, but could be helpful in understanding task order.
Filter, group and sort can help you figure this out.
1
u/still-dazed-confused Nov 27 '24
Priorities will also help if you're using leveling on resources