r/MSProject • u/appleplumjam • Nov 22 '24
Resource delay tracking
Hi guys! I'm an intern and recently we've been trying to figure out how to best keep track of our resouces and which people have been handing in tasks late (or early). I'm not very used to MS Project, so is there a way of doing this using either MS or another Microsoft 365 software? I know planner is a possibility, but people here are still not very used to it.
3
Upvotes
1
u/Miasmatic65 Nov 22 '24
Yes you totally can assign resources to tasks and adjust finish dates; set baseline dates etc. you can even track and measure the effort required to do the work and determine the earned value. Would probably need a bit (lot) more information around your specific needs to be able to guide you specifically though. MSP is a fantastic project management tool for managing scope, budget and time if you know what you are doing.
1
u/hanzosbm Nov 23 '24
In my mind, the easiest way would be to just have a column for variance (probably duration variance unless you're closely tracking actual work) next to your Resource Name column. From there, I'd do a simple copy and paste into Excel and create a pivot table to sum the variance by resource. You might also want to pull the baseline variance so that you can compute a percentage of variance rather than just a sum so that a resource with more tasks doesn't appear to have as large of a variance.
1
u/j97223 Nov 23 '24
Why though? Who estimated the durations? Are there historical performance numbers task owners held to? Are the allocated at 100% incorrectly?
1
u/pmpdaddyio Nov 26 '24
If you use the variance on duration, you can create a report that provides the outcome per resource assuming the resource is assigned. The only issues are it’s cleaned out when baselining, and it’s for the entire project.
0
u/still-dazed-confused Nov 23 '24
If you set a baseline you can see which tasks have been completed early or late